Difference between revisions of "Development G.I.S.S. Phase 3"
From Giss
Line 7: | Line 7: | ||
This phase of development is supported by the [http://nlnet.nl NLnet fundation] [[Image:Nlnet.gif]] | This phase of development is supported by the [http://nlnet.nl NLnet fundation] [[Image:Nlnet.gif]] | ||
− | == Tasks (state of | + | == Tasks (state of advancement) == |
− | === '''[[Topology of the network | + | === '''[[Topology of the network]]''' === |
''Start'' : May, 1st ''Deadline'' : June, 1st | ''Start'' : May, 1st ''Deadline'' : June, 1st | ||
− | === '''[[Distributed Multimedia Database System | + | ''Advancement'' : 100 % |
+ | |||
+ | === '''[[Distributed Multimedia Database System]]''' === | ||
''Start'' : May, 1st ''Deadline'' : August, 1st (delayed) | ''Start'' : May, 1st ''Deadline'' : August, 1st (delayed) | ||
− | === '''[[Sa'habuntu Live CD | + | ''Advancement'' : 40% |
+ | |||
+ | === '''[[Sa'habuntu Live CD]]''' === | ||
''Start'' : May, 1st ''Deadline'' : September, 1st | ''Start'' : May, 1st ''Deadline'' : September, 1st | ||
− | === '''[[G.I.S.S. Icecast | + | ''Advancement'' : 25% |
+ | |||
+ | === '''[[G.I.S.S. Icecast]]''' === | ||
''Start'' : June, 1st ''Deadline'' : November, 1st | ''Start'' : June, 1st ''Deadline'' : November, 1st | ||
− | === '''[[Workshop India | + | ''Advancement'' : 0% |
+ | |||
+ | === '''[[Workshop India]]''' === | ||
''Start'' : July, 1st ''Deadline'' : November, 1st | ''Start'' : July, 1st ''Deadline'' : November, 1st | ||
− | === '''[[Workshop Bolivia | + | ''Advancement'' : 20% |
+ | |||
+ | === '''[[Workshop Bolivia]]''' === | ||
''Start'' : September, 1st ''Deadline'' : December, 31th (delayed) | ''Start'' : September, 1st ''Deadline'' : December, 31th (delayed) | ||
+ | |||
+ | ''Advancement'' : 10% |
Revision as of 00:42, 4 June 2008
This page documents the development of G.I.S.S. Phase 3, started in May 2008 and which is planned to be finished on November 2008.
This phase of development is supported by the NLnet fundation
Contents
Tasks (state of advancement)
Topology of the network
Start : May, 1st Deadline : June, 1st
Advancement : 100 %
Distributed Multimedia Database System
Start : May, 1st Deadline : August, 1st (delayed)
Advancement : 40%
Sa'habuntu Live CD
Start : May, 1st Deadline : September, 1st
Advancement : 25%
G.I.S.S. Icecast
Start : June, 1st Deadline : November, 1st
Advancement : 0%
Workshop India
Start : July, 1st Deadline : November, 1st
Advancement : 20%
Workshop Bolivia
Start : September, 1st Deadline : December, 31th (delayed)
Advancement : 10%