Difference between revisions of "Development G.I.S.S. Phase 3"

From Giss
Line 7: Line 7:
 
== Tasks (state of avancement) ==
 
== Tasks (state of avancement) ==
  
[[Topology of the network (0%)]]
+
[[Topology of the network (0%)]]
  
''Start'' : May, 1st  
+
''Start'' : May, 1st  
  
''Deadline'' : June, 1st  
+
''Deadline'' : June, 1st  
  
[[ Distributed Multimedia Database System (0%)]]
+
[[ Distributed Multimedia Database System (0%)]]
  
''Start'' : May, 1st  
+
''Start'' : May, 1st  
  
''Deadline'' : July, 1st  
+
''Deadline'' : July, 1st  
  
[[ Sa'habuntu Live CD (0%)]]
+
[[ Sa'habuntu Live CD (0%)]]
  
''Start'' : May, 1st  
+
''Start'' : May, 1st  
  
''Deadline'' : September, 1st  
+
''Deadline'' : September, 1st  
  
[[ G.I.S.S. Icecast (0%)]]
+
[[ G.I.S.S. Icecast (0%)]]
  
''Start'' : June, 1st  
+
''Start'' : June, 1st  
  
''Deadline'' : November, 1st  
+
''Deadline'' : November, 1st  
  
[[ Workshop I (0%)]]
+
[[ Workshop I (0%)]]
  
''Start'' : July, 1st  
+
''Start'' : July, 1st  
  
''Deadline'' : September, 1st  
+
''Deadline'' : September, 1st  
  
[[ Workshop II (0%)]]
+
[[ Workshop II (0%)]]
  
''Start'' : September, 1st  
+
''Start'' : September, 1st  
  
''Deadline'' : November, 1st
+
''Deadline'' : November, 1st

Revision as of 15:30, 6 May 2008

This documents the development of G.I.S.S. Phase 3, started in May 2008 and which is planned to be finish on November 2008.

This phase of development is supported by the NLnet fundation [[1]]

Tasks (state of avancement)

Topology of the network (0%)

Start : May, 1st

Deadline : June, 1st

Distributed Multimedia Database System (0%)

Start : May, 1st

Deadline : July, 1st

Sa'habuntu Live CD (0%)

Start : May, 1st

Deadline : September, 1st

G.I.S.S. Icecast (0%)

Start : June, 1st

Deadline : November, 1st

Workshop I (0%)

Start : July, 1st

Deadline : September, 1st

Workshop II (0%)

Start : September, 1st

Deadline : November, 1st