This page documents the development of G.I.S.S. Phase 3, started in May 2008 and which is planned to be finished this year.
This phase of development is supported by the NLnet fundation
Contents
Tasks (state of advancement)
Topology of the network
Start : May, 1st Deadline : June, 1st
Advancement : 100 %
Distributed Multimedia Database System
Start : May, 1st Deadline : August, 1st (delayed)
Advancement : 40%
Sa'habuntu Live CD
Start : May, 1st Deadline : September, 1st
Advancement : 25%
G.I.S.S. Icecast
Start : June, 1st Deadline : November, 1st
Advancement : 0%
Workshop India
Start : July, 1st Deadline : November, 1st
Advancement : 20%
Workshop Bolivia
Start : September, 1st Deadline : December, 31th (delayed)
Advancement : 10%