Development G.I.S.S. Phase 3

From Giss
Revision as of 19:37, 24 May 2008 by Sevy (talk | contribs)

This documents the development of G.I.S.S. Phase 3, started in May 2008 and which is planned to be finish on November 2008.

Images:Gisstv.png

This phase of development is supported by the NLnet fundation [[1]]

Tasks (state of avancement)

Topology of the network (0%)

Start : May, 1st Deadline : June, 1st

Distributed Multimedia Database System (0%)

Start : May, 1st Deadline : July, 1st

Sa'habuntu Live CD (0%)

Start : May, 1st Deadline : September, 1st

G.I.S.S. Icecast (0%)

Start : June, 1st Deadline : November, 1st

Workshop I (0%)

Start : July, 1st Deadline : September, 1st

Workshop II (0%)

Start : September, 1st Deadline : November, 1st File:Example.jpg